Can I do a loft conversion without planning permission?

Usually, if the dormers add no more than 40 m³ of roof space on a terraced house or 50 m³ on a detached or semi-detached one, and none is on the front slope facing the road. Add your dormers and watch the allowance fill up.

Example

1. Is the house on protected land? (optional)

Dormers aren't permitted development in conservation areas, National Parks and other protected land.

Your postcode stays in your browser. We only fetch the data for its first half (for example "SW1A").

2. Your loft

Dormer (metres): width, height of its face, depth back into the roof
A second dormer (optional)

This is an example: change the figures to yours.

Likely permitted development, with things to check

Everything we can measure fits. Read the 3 points marked Check below before you build.

This is guidance, not legal advice. For certainty, apply to your council for a Lawful Development Certificate.

max 50 m³about 15.4 m³ extra roof space
max 50 m³about 15.4 m³ extra roof space
Your roof space allowance filling up: earlier additions in grey, then each dormer. The dashed orange line is the legal limit.
frontreardormer 4 m wide
frontreardormer 4 m wide
Roof cross-section with your dormer (the roof outline is illustrative).

Checked against each rule

  • Check
    Not on protected land
    Dormers aren't permitted development on protected land, which we can't rule out for your address. Enter your postcode, or answer the question.
    Source:
  • Fits
    Extra roof space: max 50 m³ (detached or semi-detached)
    Dormer 1: about 15.4 m³. Total about 15.4 m³. Limit: 50 m³. These are estimates from your measurements: measure precisely, or ask your designer, if you're close.
    Source:
  • Fits
    Not on the front roof slope facing a road
    At the back, or on a slope that doesn't face a road.
    Source:
  • Fits
    No higher than the existing roof
    The dormer stays below the ridge.
    Source:
  • Fits
    Set back from the eaves: at least 0.2 m, so far as practicable
    Yours: 0.3 m. Minimum: 0.2 m.
    Source: ,
  • Fits
    No overhang beyond the outside walls
    It doesn't overhang the outside face of the walls.
    Source:
  • Fits
    Side windows obscure-glazed and high-opening
    No windows in a side wall or side roof slope.
    Source:
  • Fits
    Materials look similar to the house
    They must look similar to the existing house: a visual judgement.
    Source:
  • Fits
    No balcony, veranda or raised platform
    None planned.
    Source:
  • Fits
    No storeys added under the upward extension rights
    No storeys have been added on top of the house under Class AA.
    Source:
  • Fits
    The house wasn't created under permitted development
    You said it wasn't.
    Source: ,
  • Check
    No Article 4 direction removes these rights
    Enter your postcode above and we'll check what your council has published.
    Source:
  • Check
    No planning condition removes these rights
    Was your house built in the last 30 years, or on an estate? A planning condition may have removed these rights. Check the council's planning register.
    Source:

3. Has a planning condition removed your loft rights?

Was your house built in the last 30 years, or on an estate? Planning conditions may have removed these rights. When a council grants planning permission for new houses, it can attach a condition that removes some or all permitted development rights, for example extensions, outbuildings or fences. This is common on newer estates. If there is such a condition, the rights in this checker do not apply and you need planning permission. Open data does not record these conditions, so this tool cannot check them for you. The 30 years is a prompt, not a legal cut-off. A condition on a permission of any age still applies.

How to check
  1. Find your council's online planning register (search for the council name and "planning applications search").
  2. Search by your address, your road name or the estate name for the permission that allowed the house to be built. On an estate this is usually the developer's application, which may list many plots.
  3. Open the decision notice and read the conditions. Look for any condition that mentions the General Permitted Development Order, "permitted development", or Part 1 (Class B: roof enlargements) of Schedule 2, or that says no dormers or other roof extensions may be put up without permission. A condition that only removes other rights (for example fences or outbuildings) doesn't affect this project.
  4. Also check any later permission for your house, such as an earlier extension. Its conditions can remove rights too.
  5. If the permission is old and not online, ask the council's planning department, or look at the local authority search in your purchase documents.
  6. If you are still unsure, ask the council or apply for a Lawful Development Certificate.
What did you find?

Loft conversions: what people ask

Do I need planning permission for a loft conversion?

Usually not, if it adds no more than 40 m³ of roof space on a terraced house or 50 m³ on a detached or semi-detached house, isn't on the front slope facing the road, and doesn't go above the ridge.

Dormers aren't permitted development in conservation areas, National Parks, the Broads, National Landscapes or World Heritage Sites. A loft conversion with only rooflights inside the existing roof is simpler again.

How big is 40 m³ or 50 m³ of roof space?

It's the extra volume your dormers (and any hip to gable) add to the roof, plus any roof additions made since 1948. A box dormer adds about half its width × height × depth: for example a dormer 4 metres wide, 2.2 metres high and 3.5 metres deep adds about 15.4 cubic metres.

Can I put a dormer on the front of my house?

Not under permitted development if the front roof slope forms the principal elevation and faces a road. Rear and side dormers are fine within the other limits.

How far from the eaves must a dormer be?

At least 0.2 m, so far as practicable, measured along the roof slope from the edge of the eaves. The original eaves must be kept, apart from a hip to gable.

Do side windows in a loft need to be obscure glass?

Yes. Any window in a side wall or side roof slope must be obscure-glazed, and can only open more than 1.7 m above the floor of the room.

Do rooflights need planning permission?

Usually not: they can stick out no more than 0.15 m from the roof slope and can't go above the ridge. Rooflights in a side slope must be obscure-glazed.

The clauses behind this checker

How we check our rules

Next steps for your house